Infrastructure & Public Works Projects

Projects

Main Street Bridge Replacement

Work involves replacing the aging structure with a new bridge that will incorporate an additional driving lane, updated lighting, improved decorative railing and wider driving lanes and sidewalks. The bridge will also be designed to provide additional clearances to handle high water incidents.

Media Release Link

Proposed details: subject to change

  • 75 year design life
  • Lane widths will be widened to 3.5 m
  • Additional driving lane added to provide 4 lanes
  • Cast in place fully integral concrete abutments which will eliminate need for bridge bearings and expansion joints
  • Concrete deck over steel plate girders
  • Vertical clearance of bridge at centre span raised about 520mm
  • Decorative railings with end blocks and light poles
  • Designed to resist water and ice loading
  • Main Street will have to be closed by up to 7 weeks.
  • Construction will use an accelerated bridge construction (ABC) method which will drastically reduce the amount of time that the street will be closed from 19 weeks down to 7

Bridge Replacement Support provided by

  • Government of Canada $1, 452,515
  • Government of Newfoundland and Labrador $1,597,767
  • City of Corner Brook $1,307,264

 

Main Street Bridge: Images of Bridge Drawing Proposed

**proposed drawings are subject to change

 


2017

Major Capital Works Construction Projects link


Combined Sewer Separation Phase 1

Cobb Lane Area